Concrete calculator

Multiply length by width by depth for a slab or footing, or multiply the circular area by height for a round column. Add the volumes and waste allowance, then divide by mixed yield and round up for bags, or round up to the supplier’s ready-mix increment if entered. Compare concrete estimates by tube size for 8 in diameter, 12 in diameter and 16 in diameter.

Measurements and materials

Pour sections

Section 1
Supply and waste

For bags, confirm the mixed yield on the label. For a truck quote, enter the volume increment only if your supplier rounds orders.

Enter prices in the same currency.

Results

Select Calculate to see results for your measurements.

Use your results

How it works

How to measure

Measure inside the forms. For a slab use the finished thickness from the compacted base to the top of the pour. Check depth in several places and split thickened edges into separate sections, counting only the extra depth beneath the slab. Use the formed trench width and fill depth for strip footings. Measure the inside diameter and fill height of round forms such as Sonotubes. For solid stairs on a level base, enter the rise and horizontal tread run of one step, the clear width and the number of equal tread blocks. Measure a separate landing separately. For a straight curb use the run length, height, base width and top width. Enter identical pieces once with a quantity.

Formula

Slab or footing = length × width × depth. Round column = π × (inside diameter ÷ 2)² × height. Solid steps = width × tread run × rise × n(n + 1) ÷ 2. Curb = length × height × (base width + top width) ÷ 2. Multiply each section by its count, sum, and add waste once. Divide by mixed volume per bag and round up, or round the ready-mix volume up to the supplier’s increment when entered.

Worked example

A 12 ft × 10 ft slab at 4 in thick with 10% waste and 80 lb bags yielding 0.60 ft³ each.

The slab takes 40 ft³ net plus 4 ft³ allowance, about 1.63 yd³ or 1.25 m³ in total. Buy 74 bags (44.4 ft³), leaving 0.4 ft³ beyond the allowance. A truck selling in 0.25 yd³ increments would supply 1.75 yd³.

What changes the result

A tube’s volume grows with the square of its diameter. Slab volume changes directly with thickness, so soft spots or low subgrade can change the order. For ready-mix, confirm the supplier’s order increment, minimum load and fees. For bagged mix, use the mixed yield printed on the product, and price a whole bag.

Questions and answers

How many bags of concrete do I need?

Divide the total volume including waste by the mixed volume per bag and round up. In the worked slab example, 44 ft³ at 0.60 ft³ per bag rounds up to 74 bags.

How do I calculate concrete for a round fence post hole?

Divide the measured inside diameter by two, square that radius, multiply by π, then multiply by the depth to be filled. Multiply by the number of identical holes and add the selected waste allowance.

How do I calculate a ready-mix order in cubic yards?

Use the total concrete volume including waste. If your supplier sells in fixed increments, enter the increment to round up the order. For example, 44 ft³ is about 1.63 yd³ and rounds up to 1.75 yd³ at a 0.25 yd³ increment.

Assumptions and sources

Bag yield examples come from QUIKRETE 1101 for 40, 50, 60 and 80 lb bags and Hanson 40N for the 25 kg bag (10 L). The yields are editable. Use the mixed yield for the product you plan to buy. The starting waste percentage is a worked example.

The steps model covers full-depth steps on a flat base with one tread per rise. Measure a landing, void or sloped underside separately. The curb model assumes a constant trapezoid cross-section. Ready-mix cost excludes delivery, short-load charges and taxes.

Use this estimate for planning. For engineering or code-compliance questions, consult a qualified professional.

Method version 1.0

Related calculators

Embed this calculator

Estimates for common sizes